Successfully implemented projects are what ultimately counts. PORR Umwelttechnik can look back on almost three decades of experience and hundreds of successfully completed orders. We work for a variety of employers in the construction industry. Public institutions rely on our expertise, as do industrial, commercial and private customers.

Our expertise and holistic approach, state-of-the-art technology and the high personal commitment of our employees are behind every one of our successfully completed projects. Here is a small selection of them. See for yourself.

Demolition of the power station Voitsberg

Photo: Demolition of the power station Voitsberg: The cooling tower collapses after being torn down.
Facts and Figures
Company PORR Umwelttechnik GmbH in a consortium
PrincipalARGE KW Voitsberg
LocationVoitsberg - Austria
Type Demolition
Runtime12.2012 - 05.2016

From the industrial ruin to "Green Field"

In the course of the implementation of the largest industrial demolition project of its time in Austria, PORR was responsible for the demolition of the former brown coal power station in Voitsberg . The professional demolition of a power plant of this magnitude - the complex has an area of 250,000 m2 on - is rare and represents a major challenge for everyone involved. Overall 35 massive power plant buildings, four of which are over 100 m high respectively, were dismantled - including the 180 m high chimney. 200,000 tons of reinforced concrete were broken up and 40,000 tons of steel scrap were dismantled for this purpose. More than 90% of the materials were processed under quality assurance standards and recycled directly on the site. After contract compliant construction of a "Green field" the properties are now ready to be utilized.

Overall, the dismantling of the power plant site mainly included:

  • Demolition of the Chimney (height: 180 m)
  • Demolition of the Boiler Room (height: 103 m)
  • Demolition of the Staircase Tower (height: 103 m)
  • Demolition of the Cooling Tower (height: 100 m)
  • Demolition of the Bunker Building (height: 54 m)
  • Property area: approx. 250,000 m2
  • Enclosed space: 150,000 m3
  • Recycling of reinforced concrete: approx. 200,000 t
  • Recycling of scrap metal: approx. 40,000 t
  • Pollutant clean-up (asbestos)
  • Dismantling radioactive measuring elements (Cs 137)