Successfully implemented projects are what ultimately counts. PORR Umwelttechnik can look back on almost three decades of experience and hundreds of successfully completed orders. We work for a variety of employers in the construction industry. Public institutions rely on our expertise, as do industrial, commercial and private customers.

Our expertise and holistic approach, state-of-the-art technology and the high personal commitment of our employees are behind every one of our successfully completed projects. Here is a small selection of them. See for yourself.

Novartis Research Centre

Photo: Demolition of Novartis Research Centre: The gutted and cleaned building is demolished using a crane.
Facts and Figures
Company PORR Umwelttechnik GmbH in a consortium
PrincipalSandoz GmbH
LocationVienna - Austria
Type Demolition
Runtime04.2013 - 09.2013

Rehabilitation, gutting and demolition

Several pollutants needed to be removed before demolition work on the former Novartis Research Centre could begin. In particular, 10,400 running metres of joints containing PCBs needed to be removed by means of high-pressure jet equipment. For this purpose, every affected part of the building needed to be secured by means of geo-textiles beforehand, to make sure no joint material would be emitted to the environment. 

Gutting work was performed at the same time to remove all lines, cables and other infrastructure from the building. The buildings thus cleaned were then demolished. 124,000t of demolition material were treated and re-used at the construction site.